Projects
Thirty-five years,mapped.
Every project on the record, plotted at its site. Filter by discipline, or open a project for its scope, era and role.
- Projects on record
- 51
- MWe of generation
- 6,662
- Since
- 1989
Proof,not promises.
A selection from a record of more than fifty projects taken to Final Acceptance.
EBoP engineering, design and material supply for five combined-cycle plants — Taza, Rumaila, Baiji 1 & 2 and Nasiriyah.
- Location
- Iraq — five plants
- Period
- 2006–2016
- GPS
- 35.33° N · 44.33° E
Systems integration for Ankara City Hospital: 20+ low-voltage systems, 600+ personnel, margin raised from <10% to 17%+, and a 10-year service contract secured.
- Location
- Ankara
- Period
- 2016–2021
- GPS
- 39.96° N · 32.78° E
Two 135 MWe units with EBoP and 154 kV switchyard, integrated with Akköy I and taken to Final Acceptance.
- Location
- Kürtün, Gümüşhane
- Period
- 2006–2016
- GPS
- 40.70° N · 38.90° E
A 380/154/33 kV substation for TEİAŞ, negotiated at target margin with procedures in place for future scope from Enerjisa.
- Location
- Mersin
- Period
- 2024–2025
- GPS
- 36.92° N · 34.90° E
Nineteen 3.2 MWe turbines with electrical balance of plant and a 154 kV switchyard in Vize, Kırklareli.
- Location
- Vize, Kırklareli
- Period
- 2006–2016
- GPS
- 41.57° N · 27.77° E
A hybrid plant pairing 2.5 MWe of solar with 5 MWe of battery storage for Eninde Energy.
- Location
- Şanlıurfa
- Period
- 2024
- GPS
- 37.75° N · 39.32° E
The full ledger (51)
- Siverek SPP + BESS7.5 MWeŞanlıurfa2.5 MWe solar plant with 5 MWe battery storage
- Hungary SPP28 MWeHungary28/64 MWe solar power plant
- BOTAŞ Silivri NGSP2021–2025Silivri, İstanbulOffshore underground natural gas storage
- TEİAŞ Tarsus OSB TM2024–2025Mersin400 kV substation, 380/154/33 kV
- EÜAŞ MobilePac175 MWeMultiple sites7 × 25 MWe FT8 mobile power station upgrades
- TEİAŞ Selimiye GIS2024–2025Selimiye154/36 kV gas-insulated substation, warranty period
- Hacıhıdırlar WPP2024–2025Türkiye154 kV switchyard and overhead line
- Bilkent Integrated Health Campus2016–2021Ankara$1.3B campus — 20+ integrated low-voltage systems, 600+ personnel
- Turkcell Datacenter2016–2021ÇorluFire alarm and FM-200 extinguishing systems
- Dem İlaç Production Facility2016–2021YalovaBMS, KNX, fire alarm and FM-200
- Siemens Gebze Facility1 MWeGebze1 MWe solar plant, CCTV, access control, fire alarm
- Anot Group2016–2021EskişehirEnergy efficiency and integrated security
- Mondialenobel Factories 1 & 22016–2021LüleburgazFire alarm and FM-200 extinguishing systems
- Iraq-5PP CCPP3,990 MWeIraq — five plantsEBoP engineering, design and supply — Taza, Rumaila, Baiji 1 & 2, Nasiriyah
- Akköy II HEPP270 MWeKürtün, Gümüşhane2 × 135 MWe EBoP and 154 kV switchyard
- Kargı Dam & HEPP100 MWeOsmancık, Çorum2 × 50 MWe EBoP, 154 kV switchyard and OHL
- Akköprü Dam & HEPP100 MWeDalaman, Muğla2 × 50 MWe EBoP and 154 kV switchyard
- Uluabat HEPP100 MWeNilüfer, Bursa2 × 50 MWe EBoP, 154 kV switchyard and civil works
- Uzunçayır HEPP84 MWeMunzur, Tunceli3 × 28 MWe EBoP and 154 kV switchyard
- Akocak HEPP80 MWeAraklı, Trabzon2 × 40 MWe EBoP, 154 kV switchyard and civil works
- Burçak 1 & 2 HEPP73.7 MWeŞebinkarahisar, Giresun73.7 MWe across two plants, EBoP, I&C and 154 kV OHL
- Uzundere HEPP62 MWeİkizdere, Rize2 × 31 MWe EBoP and MV switchgear
- Balkusan 1 & 2 HEPP47 MWeErmenek, Karaman47 MWe across two plants, EBoP and I&C
- Koçlu HEPP36 MWeYağlıdere, Giresun2 × 18 MWe EBoP, I&C and 154 kV switchyard
- Ören HEPP28 MWeBulancak, Giresun4 × 7 MWe EBoP and I&C
- Egemen 1 & 2 HEPP22 MWeOsmangazi, Bursa22 MWe across two plants, EBoP and I&C
- Kayabükü HEPP15 MWeMengen, Bolu3 × 5 MWe EBoP and I&C
- Airres4 WPP60.8 MWeVize, Kırklareli19 × 3.2 MWe EBoP and 154 kV switchyard
- Poyraz WPP32 MWeSusurluk, Balıkesir10 × 3.2 MWe EBoP and 154 kV switchyard
- Acarsoy CCPP Switchyard2006–2016Honaz, Denizli154 kV switchyard, 6 feeders, and OHL
- TEİAŞ Hayrat Switchyard2006–2016Hayrat, Trabzon154 kV switchyard EBoP, 6 feeders
- TEİAŞ İkitelli Switchyard2001–2006İstanbul380 kV — HV circuit-breaker renewals on 6 feeders and 2 feeder extensions for HV cable
- Çerkezköy OSB CCPP Switchyard2001–2006Tekirdağ154 kV switchyard, 9 feeders, civil works and OHL
- EÜAŞ Hamitabat CCPP2001–2006Kırklareli154 kV switchyard feeder extension
- TEİAŞ Çerkezköy Switchyard2001–2006Çerkezköy, Tekirdağ154 kV feeder extension, OHL, 1.9 km concrete cable trench and 36 kV XLPE cables
- TEİAŞ Ambarlı Switchyard2001–2006Ambarlı, İstanbul154 kV switchyard feeder extension
- TEİAŞ Habipler Switchyard2001–2006Habipler, İstanbul154 kV switchyard feeder extension
- TEİAŞ Kırklareli Switchyard2001–2006Kırklareli154 kV switchyard feeder extension
- TEİAŞ Çorlu / Ulaş Switchyard2001–2006Çorlu, Tekirdağ154 kV switchyard, 4 feeder extensions
- Modern Enerji / Ulaş Switchyard2001–2006Ulaş, Trakya154 kV switchyard
- Grand National Assembly (TBMM)1996–2001AnkaraConference, biometric voting and simultaneous translation systems
- Selatin Tunnel1996–2001İzmir–AydınSCADA, CCTV, public address and fire alarm
- BSH Profilo Factory1996–2001Çerkezköy, TekirdağFire alarm in 10,000+ locations, CCTV and access control
- Arçelik Factory1996–2001Çayırova, KocaeliCCTV, security and access control systems
- Siemens Kartal Campus1996–2001Kartal, İstanbulIntegrated security: CCTV, intrusion detection, access control and fire alarm
- Harbiye Military Museum1996–2001Harbiye, İstanbulIntrusion and environmental security, CCTV
- İMKB — İstanbul Stock Exchange1996–2001İstinye, İstanbulAccess control system
- Marks & Spencer Mall Şaşkınbakkal1996–2001Şaşkınbakkal, İstanbulCCTV and security, access control, public address and fire alarm
- Siemens Ankara Office1996–2001AnkaraCCTV, access control, security and fire alarm
- Hotels & Residential Blocks1996–2001İstanbul & AntalyaMATV/CATV, fire alarm and public address commissioning — IBS, Adora Hotel, Conrad Hotel, Ataköy, Naciye Sultan and Otağtepe blocks
- Ambarlı CCPP1,350 MWeİstanbul1,350 MWe — 380 kV switchyard testing, TELEPERM ME commissioning
Let’s energiseyour project.
Tell us where your project stands. You will hear back from Levent directly, usually within one business day.