Thermal & Gas · 2024–2025
EÜAŞ MobilePac
7 × 25 MWe FT8 mobile power station upgrades — Multiple sites.
01Context
Delivered by Bahtiyar Levent Belgin as Deputy General Manager, HV Projects at EMTA Elektrik. The scope, figures and period reflect his project record.
- Scope
- 7 × 25 MWe FT8 mobile power station upgrades
- Location
- Multiple sites
- Period
- 2024–2025
- Generation capacity
- 175 MWe
- Discipline
- Oil, gas & thermal power
- Organisation
- EMTA Elektrik
- Role
- Deputy General Manager, HV Projects