01 / 07
Wind
Electrical balance of plant, 154 kV switchyards and grid connection for onshore wind farms — from design review to energisation.
On record
Airres4 WPP · 19 × 3.2 MWe · Kırklareli
Energy infrastructure · project management & consultancy
For 35 years, Bahtiyar Levent Belgin has taken power plants, substations and transmission lines from signed contract to Final Acceptance — across Türkiye, Europe and the Middle East. Belgineer brings that record to your project.
Why Belgineer
Energy projects rarely fail on engineering. They fail at the interfaces — between owners and contractors, grids and governments, schedules and site reality. For more than three decades, that is exactly where Levent Belgin has worked.
The record, in numbers
Generation capacity delivered across his project record
Years in power-sector delivery and leadership
Largest single programme — Bilkent Integrated Health Campus
Personnel led on a single project
Projects taken to Final Acceptance
Generation, storage, transmission and the mission-critical buildings they power — managed end to end, from engineering review to operations handover.
01 / 07
Electrical balance of plant, 154 kV switchyards and grid connection for onshore wind farms — from design review to energisation.
On record
Airres4 WPP · 19 × 3.2 MWe · Kırklareli
02 / 07
Utility-scale photovoltaic plants in Türkiye and Europe, delivered as standalone or hybrid solar-plus-storage assets.
On record
Hungary SPP · 28/64 MWe
03 / 07
Dams and run-of-river plants in some of Türkiye’s most demanding terrain — fourteen hydro plants taken to Final Acceptance.
On record
Akköy II HEPP · 2 × 135 MWe · Gümüşhane
04 / 07
Battery energy storage integrated with generation and grid for firming, frequency response and peak shaving.
On record
Siverek SPP + BESS · 5 MWe storage · Şanlıurfa
05 / 07
Substations up to 400 kV, gas-insulated switchgear, overhead lines and switchyard extensions for TEİAŞ and private owners.
On record
TEİAŞ Tarsus OSB · 380/154/33 kV
06 / 07
Combined-cycle plants, mobile gas turbines and gas storage — dispatchable capacity delivered at national scale.
On record
Iraq-5PP · 3,990 MWe · five plants
07 / 07
Mission-critical buildings — hospitals, data centres, a national parliament — with dozens of integrated systems under one programme.
On record
Bilkent Health Campus · $1.3B · Ankara
Every era added a layer: commissioning, site command, programme management, P&L, turnaround.
1989 — 1994
Simko · Siemens AG
General Supervisory Representative
Simko · Siemens AG
General Supervisory Representative
1989 — 1994
General Supervisory Representative
Commissioning at the 1,350 MWe Ambarlı combined-cycle plant: 380 kV switchyard testing and TELEPERM ME control system programming.
1996 — 2006
Project Controlling & Site Manager
380 kV and 154 kV switchyards for TEİAŞ, and integrated conference and biometric voting systems for the Grand National Assembly.
2006 — 2016
Project Manager
Fourteen hydro plants, two wind farms and ~4 GW of combined-cycle EBoP engineering for five plants in Iraq.
2016 — 2021
Project Group Manager
Led 600+ people on the $1.3B Bilkent Integrated Health Campus and lifted contract margin from under 10% to over 17%.
2021 — today
General Manager & Principal Consultant
Senior project management consultancy for owners and EPCs across EMEA: solar, storage, gas storage, high voltage.
2024 — 2025
Deputy General Manager, HV Projects
Turned around takeover projects — cost projections cut by 50%+, delivery pulled forward two years — and won ₺3B+ in new HV tenders.
A selection from a record of more than fifty projects taken to Final Acceptance.
EBoP engineering, design and material supply for five combined-cycle plants — Taza, Rumaila, Baiji 1 & 2 and Nasiriyah.
Systems integration for Ankara City Hospital: 20+ low-voltage systems, 600+ personnel, margin raised from <10% to 17%+, and a 10-year service contract secured.
Two 135 MWe units with EBoP and 154 kV switchyard, integrated with Akköy I and taken to Final Acceptance.
A 380/154/33 kV substation for TEİAŞ, negotiated at target margin with procedures in place for future scope from Enerjisa.
Nineteen 3.2 MWe turbines with electrical balance of plant and a 154 kV switchyard in Vize, Kırklareli.
A hybrid plant pairing 2.5 MWe of solar with 5 MWe of battery storage for Eninde Energy.
| Project | Location | Scope | Period |
|---|---|---|---|
| Siverek SPP + BESS | Şanlıurfa | 2.5 MWe solar plant with 5 MWe battery storage | 2024 |
| Hungary SPP | Hungary | 28/64 MWe solar power plant | 2021–2025 |
| BOTAŞ Silivri NGSP | Silivri, İstanbul | Offshore underground natural gas storage | 2021–2025 |
| TEİAŞ Tarsus OSB TM | Mersin | 400 kV substation, 380/154/33 kV | 2024–2025 |
| EÜAŞ MobilePac | Multiple sites | 7 × 25 MWe FT8 mobile power station upgrades | 2024–2025 |
| TEİAŞ Selimiye GIS | Selimiye | 154/36 kV gas-insulated substation, warranty period | 2024–2025 |
| Hacıhıdırlar WPP | Türkiye | 154 kV switchyard and overhead line | 2024–2025 |
| Bilkent Integrated Health Campus | Ankara | $1.3B campus — 20+ integrated low-voltage systems, 600+ personnel | 2016–2021 |
| Turkcell Datacenter | Çorlu | Fire alarm and FM-200 extinguishing systems | 2016–2021 |
| Dem İlaç Production Facility | Yalova | BMS, KNX, fire alarm and FM-200 | 2016–2021 |
| Siemens Gebze Facility | Gebze | 1 MWe solar plant, CCTV, access control, fire alarm | 2016–2021 |
| Anot Group | Eskişehir | Energy efficiency and integrated security | 2016–2021 |
| Mondialenobel Factories 1 & 2 | Lüleburgaz | Fire alarm and FM-200 extinguishing systems | 2016–2021 |
| Iraq-5PP CCPP | Iraq — five plants | EBoP engineering, design and supply — Taza, Rumaila, Baiji 1 & 2, Nasiriyah | 2006–2016 |
| Akköy II HEPP | Kürtün, Gümüşhane | 2 × 135 MWe EBoP and 154 kV switchyard | 2006–2016 |
| Kargı Dam & HEPP | Osmancık, Çorum | 2 × 50 MWe EBoP, 154 kV switchyard and OHL | 2006–2016 |
| Akköprü Dam & HEPP | Dalaman, Muğla | 2 × 50 MWe EBoP and 154 kV switchyard | 2006–2016 |
| Uluabat HEPP | Nilüfer, Bursa | 2 × 50 MWe EBoP, 154 kV switchyard and civil works | 2006–2016 |
| Uzunçayır HEPP | Munzur, Tunceli | 3 × 28 MWe EBoP and 154 kV switchyard | 2006–2016 |
| Akocak HEPP | Araklı, Trabzon | 2 × 40 MWe EBoP, 154 kV switchyard and civil works | 2006–2016 |
| Burçak 1 & 2 HEPP | Şebinkarahisar, Giresun | 73.7 MWe across two plants, EBoP, I&C and 154 kV OHL | 2006–2016 |
| Uzundere HEPP | İkizdere, Rize | 2 × 31 MWe EBoP and MV switchgear | 2006–2016 |
| Balkusan 1 & 2 HEPP | Ermenek, Karaman | 47 MWe across two plants, EBoP and I&C | 2006–2016 |
| Koçlu HEPP | Yağlıdere, Giresun | 2 × 18 MWe EBoP, I&C and 154 kV switchyard | 2006–2016 |
| Ören HEPP | Bulancak, Giresun | 4 × 7 MWe EBoP and I&C | 2006–2016 |
| Egemen 1 & 2 HEPP | Osmangazi, Bursa | 22 MWe across two plants, EBoP and I&C | 2006–2016 |
| Kayabükü HEPP | Mengen, Bolu | 3 × 5 MWe EBoP and I&C | 2006–2016 |
| Airres4 WPP | Vize, Kırklareli | 19 × 3.2 MWe EBoP and 154 kV switchyard | 2006–2016 |
| Poyraz WPP | Susurluk, Balıkesir | 10 × 3.2 MWe EBoP and 154 kV switchyard | 2006–2016 |
| Acarsoy CCPP Switchyard | Honaz, Denizli | 154 kV switchyard, 6 feeders, and OHL | 2006–2016 |
| TEİAŞ Hayrat Switchyard | Hayrat, Trabzon | 154 kV switchyard EBoP, 6 feeders | 2006–2016 |
| TEİAŞ İkitelli Switchyard | İstanbul | 380 kV — HV circuit-breaker renewals on 6 feeders and 2 feeder extensions for HV cable | 2001–2006 |
| Çerkezköy OSB CCPP Switchyard | Tekirdağ | 154 kV switchyard, 9 feeders, civil works and OHL | 2001–2006 |
| EÜAŞ Hamitabat CCPP | Kırklareli | 154 kV switchyard feeder extension | 2001–2006 |
| TEİAŞ Çerkezköy Switchyard | Çerkezköy, Tekirdağ | 154 kV feeder extension, OHL, 1.9 km concrete cable trench and 36 kV XLPE cables | 2001–2006 |
| TEİAŞ Ambarlı Switchyard | Ambarlı, İstanbul | 154 kV switchyard feeder extension | 2001–2006 |
| TEİAŞ Habipler Switchyard | Habipler, İstanbul | 154 kV switchyard feeder extension | 2001–2006 |
| TEİAŞ Kırklareli Switchyard | Kırklareli | 154 kV switchyard feeder extension | 2001–2006 |
| TEİAŞ Çorlu / Ulaş Switchyard | Çorlu, Tekirdağ | 154 kV switchyard, 4 feeder extensions | 2001–2006 |
| Modern Enerji / Ulaş Switchyard | Ulaş, Trakya | 154 kV switchyard | 2001–2006 |
| Grand National Assembly (TBMM) | Ankara | Conference, biometric voting and simultaneous translation systems | 1996–2001 |
| Selatin Tunnel | İzmir–Aydın | SCADA, CCTV, public address and fire alarm | 1996–2001 |
| BSH Profilo Factory | Çerkezköy, Tekirdağ | Fire alarm in 10,000+ locations, CCTV and access control | 1996–2001 |
| Arçelik Factory | Çayırova, Kocaeli | CCTV, security and access control systems | 1996–2001 |
| Siemens Kartal Campus | Kartal, İstanbul | Integrated security: CCTV, intrusion detection, access control and fire alarm | 1996–2001 |
| Harbiye Military Museum | Harbiye, İstanbul | Intrusion and environmental security, CCTV | 1996–2001 |
| İMKB — İstanbul Stock Exchange | İstinye, İstanbul | Access control system | 1996–2001 |
| Marks & Spencer Mall Şaşkınbakkal | Şaşkınbakkal, İstanbul | CCTV and security, access control, public address and fire alarm | 1996–2001 |
| Siemens Ankara Office | Ankara | CCTV, access control, security and fire alarm | 1996–2001 |
| Hotels & Residential Blocks | İstanbul & Antalya | MATV/CATV, fire alarm and public address commissioning — IBS, Adora Hotel, Conrad Hotel, Ataköy, Naciye Sultan and Otağtepe blocks | 1996–2001 |
| Ambarlı CCPP | İstanbul | 1,350 MWe — 380 kV switchyard testing, TELEPERM ME commissioning | 1989–1994 |

General Manager & Principal Consultant
An electrical engineer by training, an economist by second degree, and a project director by thirty-five years of practice. Levent has commissioned switchyards, run site organisations and led 600-person programmes — so he knows what every layer of a project needs from the one above it.
01
Engineering review
02
Procurement & contracts
03
Construction
04
Testing & commissioning
05
Final acceptance
06
Operations handover
We sit on the owner’s side of the table through the full lifecycle — schedule, cost, quality and interfaces under one lead.
Distressed or taken-over projects re-baselined, contracts renegotiated and delivery pulled back on schedule.
Bid strategy, contract structuring, variations and claims — so commercial risk is priced before it is inherited.
Risk registers, QA/QC systems, ISO 14001 discipline and a site safety culture that holds up under audit.
Tell us where your project stands. You will hear back from Levent directly, usually within one business day.