Thermal & Gas · 2006–2016

Iraq-5PP CCPP

EBoP engineering, design and material supply for five combined-cycle plants — Taza, Rumaila, Baiji 1 & 2 and Nasiriyah.

3,990MWe

GTHRSGCCPPDWG BLG-01 · REV ASCALE NTS
01Context

Delivered by Bahtiyar Levent Belgin as Project Manager at Siemens Power Generation. The scope, figures and period reflect his project record.

Scope
EBoP engineering, design and supply — Taza, Rumaila, Baiji 1 & 2, Nasiriyah
Location
Iraq — five plants
Period
2006–2016
Generation capacity
3,990 MWe
Organisation
Siemens Power Generation
Role
Project Manager
Coordinates
35.33° N, 44.33° E