Hydro · 2006–2016

Akocak HEPP

2 × 40 MWe EBoP, 154 kV switchyard and civil works — Araklı, Trabzon.

DAM2 × 135 MWeDWG BLG-01 · REV ASCALE NTS
01Context

Delivered by Bahtiyar Levent Belgin as Project Manager at Siemens Power Generation. The scope, figures and period reflect his project record.

Scope
2 × 40 MWe EBoP, 154 kV switchyard and civil works
Location
Araklı, Trabzon
Period
2006–2016
Generation capacity
80 MWe
Discipline
Hydroelectric
Organisation
Siemens Power Generation
Role
Project Manager
Coordinates
40.90° N, 40.05° E