Hydro · 2006–2016
Uluabat HEPP
2 × 50 MWe EBoP, 154 kV switchyard and civil works — Nilüfer, Bursa.
01Context
Delivered by Bahtiyar Levent Belgin as Project Manager at Siemens Power Generation. The scope, figures and period reflect his project record.
- Scope
- 2 × 50 MWe EBoP, 154 kV switchyard and civil works
- Location
- Nilüfer, Bursa
- Period
- 2006–2016
- Generation capacity
- 100 MWe
- Discipline
- Hydroelectric
- Organisation
- Siemens Power Generation
- Role
- Project Manager
- Coordinates
- 40.08° N, 28.85° E