Wind · Transmission · 2006–2016
Poyraz WPP
10 × 3.2 MWe EBoP and 154 kV switchyard — Susurluk, Balıkesir.
01Context
Delivered by Bahtiyar Levent Belgin as Project Manager at Siemens Power Generation. The scope, figures and period reflect his project record.
- Scope
- 10 × 3.2 MWe EBoP and 154 kV switchyard
- Location
- Susurluk, Balıkesir
- Period
- 2006–2016
- Generation capacity
- 32 MWe
- Discipline
- Wind energyTransmission & substations
- Organisation
- Siemens Power Generation
- Role
- Project Manager
- Coordinates
- 39.91° N, 28.15° E