Services · Renewable energy · Solar

Solar plants that reach full output.

Photovoltaic plants look simple on a drawing: rows of modules, inverters, a substation. Delivering them on budget depends on disciplined procurement, installation quality and a grid connection that is ready when the last string is.

28/64

MWe — Hungary SPP

2.5 + 5

MWe solar + storage — Siverek

PV ARRAY · TRACKING28 / 64 MWeDWG BLG-01 · REV ASCALE NTS
01From land to export meter

Solar schedules are compressed and margins are thin. Module and inverter prices move, installation crews scale quickly, and the grid connection often becomes the critical path. The owner needs one party watching quality, cost and interfaces at the same time.

Belgineer manages utility-scale PV for owners and EPC contractors, including the Hungary SPP (28/64 MWe) and the Siverek hybrid plant in Şanlıurfa, where 2.5 MWe of solar was paired with 5 MWe of battery storage. Earlier, as a Siemens Smart Infrastructure project group manager, Levent Belgin also delivered a 1 MWe rooftop plant at Siemens’ Gebze facility.

02What we deliver
  1. 01

    Owner’s engineering

    Design review of layouts, string design, inverter selection and the MV/HV connection before procurement.

  2. 02

    Procurement strategy

    Module, inverter and BoP packages structured to protect price and delivery in volatile supply markets.

  3. 03

    Construction oversight

    Installation quality, earthing, cabling and QA/QC inspections tracked against a single schedule.

  4. 04

    Hybrid solar + storage

    Integration of battery energy storage with PV — control philosophy, grid code compliance and commissioning.

  5. 05

    Grid connection

    Substation, protection and connection agreements coordinated with the network operator.

  6. 06

    Performance & acceptance

    Commissioning tests, performance verification and Final Acceptance with a complete documentation set.

03How we de-risk it
  1. 01

    Fix the design before the price

    Layouts and electrical design are validated so procurement buys the right equipment once.

  2. 02

    Buy against a plan

    Procurement is sequenced to the construction programme, not the other way round.

  3. 03

    Inspect as you build

    Quality is checked row by row, so defects never reach commissioning.

  4. 04

    Prove the output

    Acceptance is based on measured performance, not a checklist.

04On the record

3 projects36.5 MWe of generation

Projects in this discipline, plotted where they were built.

05Questions, answered

What does an owner’s engineer do on a solar project?

The owner’s engineer protects the investor: reviewing design and contracts, monitoring construction quality and schedule, verifying tests and confirming the plant meets its contractual performance before acceptance.

Can solar plants be combined with battery storage?

Yes. Hybrid PV + BESS plants shift energy to higher-value hours, firm output and support the grid. Belgineer delivered this configuration at the Siverek SPP + BESS project in Şanlıurfa.

Does Belgineer work on solar projects outside Türkiye?

Yes — the Hungary SPP is an example. Belgineer supports owners and contractors across Europe and the Middle East.

At what stage should a project manager be appointed?

Ideally before the EPC contract is signed, when design and contract terms can still be shaped. Belgineer also joins projects already in construction.