Services · Renewable energy · Wind
Wind farms,connected and energised.
A wind farm earns nothing until its last turbine exports to the grid. Belgineer manages the electrical balance of plant, substation and grid interface that turn a row of turbines into a revenue-generating power plant.
19 × 3.2
MWe turbines at Airres4 WPP
154 kV
Switchyards delivered for wind
Turbine supply is usually the most visible contract on a wind project, and the most standardised. The schedule risk sits elsewhere: in the medium-voltage collector system, the step-up substation, the transmission operator’s connection requirements and the testing that must be witnessed before energisation.
Levent Belgin managed the electrical balance of plant and 154 kV switchyards for the Airres4 (19 × 3.2 MWe) and Poyraz (10 × 3.2 MWe) wind farms as a Siemens project manager, and later the 154 kV switchyard and overhead line scope for Hacıhıdırlar WPP. Belgineer brings that interface discipline to owners and EPC contractors from early design review through to Final Acceptance.
- 01
Electrical balance of plant
MV collector cabling, turbine transformers, earthing and SCADA integration — engineered, procured and installed to one coordinated plan.
- 02
Switchyard & substation
154 kV step-up substations and switchyard extensions: design review, equipment specification, protection and control.
- 03
Grid connection
Interface management with the transmission operator — connection agreements, protection coordination and energisation procedures.
- 04
Contract & schedule control
EPC and supply packages tracked on one critical path, with variations and claims controlled before they compound.
- 05
Testing & commissioning
Pre-commissioning, witnessed tests and energisation sequencing through to commercial operation.
- 06
Warranty & handover
Punch-list closure, documentation and structured handover so the operator inherits a plant — not a problem list.
01
Review the single-line early
Collector, substation and grid design are challenged before procurement, when changes are cheap.
02
Lock the interfaces
Every hand-off between turbine supplier, BoP contractor and grid operator has a named owner and a date.
03
Sequence for energisation
Civil, electrical and turbine erection are planned backwards from the first export date.
04
Close out to FAC
Warranty obligations, defects and documentation are driven to Final Acceptance, not left to drift.
3 projects92.8 MWe of generation
Projects in this discipline, plotted where they were built.
What is electrical balance of plant (EBoP) on a wind farm?
EBoP covers everything electrical outside the turbines themselves: medium-voltage collector cables, turbine transformers, the substation and switchyard, protection, earthing and the SCADA that ties it together. It is where most wind grid-connection delays originate.
Can Belgineer join a wind project that is already under construction?
Yes. Belgineer regularly steps into projects mid-stream — reviewing the schedule and contracts, stabilising interfaces between contractors and driving the remaining scope to energisation and Final Acceptance.
Which markets does Belgineer cover for wind?
Türkiye is the core market, with experience across Europe and the Middle East. Delivery combines Turkish regulatory knowledge with international EPC and OEM practice.
Do you work for owners or for contractors?
Both. Belgineer acts as the owner’s project management consultancy, or supports EPC contractors with project direction, contract management and recovery.
01
Transmission & substations
Substations to 400 kV, GIS, overhead lines and switchyard extensions.
02
Battery storage (BESS)
Battery energy storage integrated with generation and grid — firming, frequency, peak shaving.
03
Turnkey delivery & PMC
One accountable lead from engineering review to operations handover.