Services · Renewable energy · Wind

Wind farms,connected and energised.

A wind farm earns nothing until its last turbine exports to the grid. Belgineer manages the electrical balance of plant, substation and grid interface that turn a row of turbines into a revenue-generating power plant.

19 × 3.2

MWe turbines at Airres4 WPP

154 kV

Switchyards delivered for wind

154 kVHUB3.2 MWeDWG BLG-01 · REV ASCALE NTS
01Where wind projects are won or lost

Turbine supply is usually the most visible contract on a wind project, and the most standardised. The schedule risk sits elsewhere: in the medium-voltage collector system, the step-up substation, the transmission operator’s connection requirements and the testing that must be witnessed before energisation.

Levent Belgin managed the electrical balance of plant and 154 kV switchyards for the Airres4 (19 × 3.2 MWe) and Poyraz (10 × 3.2 MWe) wind farms as a Siemens project manager, and later the 154 kV switchyard and overhead line scope for Hacıhıdırlar WPP. Belgineer brings that interface discipline to owners and EPC contractors from early design review through to Final Acceptance.

02What we deliver
  1. 01

    Electrical balance of plant

    MV collector cabling, turbine transformers, earthing and SCADA integration — engineered, procured and installed to one coordinated plan.

  2. 02

    Switchyard & substation

    154 kV step-up substations and switchyard extensions: design review, equipment specification, protection and control.

  3. 03

    Grid connection

    Interface management with the transmission operator — connection agreements, protection coordination and energisation procedures.

  4. 04

    Contract & schedule control

    EPC and supply packages tracked on one critical path, with variations and claims controlled before they compound.

  5. 05

    Testing & commissioning

    Pre-commissioning, witnessed tests and energisation sequencing through to commercial operation.

  6. 06

    Warranty & handover

    Punch-list closure, documentation and structured handover so the operator inherits a plant — not a problem list.

03How we de-risk it
  1. 01

    Review the single-line early

    Collector, substation and grid design are challenged before procurement, when changes are cheap.

  2. 02

    Lock the interfaces

    Every hand-off between turbine supplier, BoP contractor and grid operator has a named owner and a date.

  3. 03

    Sequence for energisation

    Civil, electrical and turbine erection are planned backwards from the first export date.

  4. 04

    Close out to FAC

    Warranty obligations, defects and documentation are driven to Final Acceptance, not left to drift.

04On the record

3 projects92.8 MWe of generation

Projects in this discipline, plotted where they were built.

05Questions, answered

What is electrical balance of plant (EBoP) on a wind farm?

EBoP covers everything electrical outside the turbines themselves: medium-voltage collector cables, turbine transformers, the substation and switchyard, protection, earthing and the SCADA that ties it together. It is where most wind grid-connection delays originate.

Can Belgineer join a wind project that is already under construction?

Yes. Belgineer regularly steps into projects mid-stream — reviewing the schedule and contracts, stabilising interfaces between contractors and driving the remaining scope to energisation and Final Acceptance.

Which markets does Belgineer cover for wind?

Türkiye is the core market, with experience across Europe and the Middle East. Delivery combines Turkish regulatory knowledge with international EPC and OEM practice.

Do you work for owners or for contractors?

Both. Belgineer acts as the owner’s project management consultancy, or supports EPC contractors with project direction, contract management and recovery.